Sea Launch Project
High Spots
XM Radio-3 Launch
CHRONOLOGY OF ACTIVITIES
December 21, 2004 - February 1, 2005 |
Home Port activities:
- SC fueling, tests, ILV integration
- ILV transfer and "dry roll-out"
|
February 2, 2005 - February 14, 2005 |
ACS and LP sea transit to the launch site |
February 15-18, 2005 |
Pre-launch processing |
February 19, 2005 |
A decision was made to return ILV to hangar because of bad weather forecast. |
February 21-23, 2005 |
Pre-launch processing was resumed based on a good weather forecast |
February 23, 2005 |
The countdown was aborted at 7 min 8 sec before scheduled lift-off due to an off-nominal situation on the Zenit-2S. |
February 23, 2005 - February 28, 2005 |
Activities to analyze and correct the causes and effects of the off-nominal situation on the LV |
March 1, 2005 |
At 6 hours 51 min. Moscow Time (February 28, 2005 at 19 hours 51 mn. Pacific Time) the 15th launch
from the launch platform Odyssey was accomplished. XM Radio-3 spacecraft was put into its target orbit.
|
Post-launch operations, the start of the sea transit to the Home Port. |
LAUNCH RESULTS
XM Radio-3 has been put into its target orbit:
Perigee altitude, km |
Apogee altitude, km |
Inclination, deg. |
2468 |
35786 |
0 |
This launch resulted in the most precise orbital insertion
of a spacecraft in the entire history of the Sea launch
program.