BIRTH OF THE PROJECT
INTEGRTED TESTS
DEMO LAUNCH
"DirecTV-1R"
"ICO-F1"
"PanAmSat-9"
"Thuraya"
"XM Radio-2"
"XM Radio-1"
Galaxy-IIIC
Thuraya D2
EchoStar-IX
Galaxy-XIII/Horizons-1
Telstar 14/Estrela do Sul 1
DirecTV 7S
Telsat 18
XM Radio-3
Spaceway-1
Intelsat Americas-8
Inmarsat-4
Echostar-10
JCSat-9
Galaxy 16
KoreaSat 5
XM Radio-4
New Skies-8
Thuraya D3
DirecTV 11
Galaxy 18
EchoStar XI Galaxy 19 SICRAL  1B

 
homepage

sea launch

high spots
ICO-F1 LAUNCH ABORT

Russian
   

CHRONOLOGY OF ACTIVITIES

December 24, 1999 - February 7, 2000 Preparation for ILV assembly.
February 8-23, 2000 ILV assembly.
February 24, 2000

ILV transfer from ACS to LP.

February 25-27, 2000

Performance of two ILV tests under the Dry Roll-Out program.

February 27 - March 9, 2000

LP/ACS transit to the launch site.

March 10-13, 2000 Pre-launch processing at the launch site.
March 12, 2000

ICO-F1 launch at 6:49:15 A.M. Eastern Pacific Time. ILV Stage 2 launch abort on the 471st second.

The failure cause analysis panel has stated that the launch abort was caused by the non-issue (during launch processing 105 s prior to launch) of a command to close a electropneumatic valve (ÝÏÊ ÂÇÒ23) of LV Stage 2 pneumatic system from the Ground Complex of Automated Control Systems of Processing and Launch. As a result of it, due to considerable gas release from LV Stage 2 onboard bottles the starting and operation of LV Stage 2 steering engine were performed in off-nominal conditions with subsequent unauthorized termination of steering engine operation. The absence of a command to close ÝÏÊ ÂÇÒ23 in the pre-launch processing control law was the result of a logical mistake made by the developer during the control law updating prior to launch of Zenit-3SL ILV with ICO-F1 SC.

 

 

 

 